Why Indiaprecast

Why Hollow core slab manufactured from our Plant & Machinery is Better & Economical compared to any European or American Plant and Machinery?

Sr.
No.
European
machineries
Our machineries
1 Shed for Installing plant Heavy Industrial shed required. No need - Open to sky. During Rains install temporary plastic shed.
2 Casting beds for Extrusion of Hollow core slabs Expensive Steel Bed (Cassette type) used. On smooth & well-leveled Concrete floor beds
3 Length of bed & No. of Casting beds for Extrusion of Hollow core slabs. Length : 130 to 150 Meters
Casting Beds : 4
Length : 130 to 150 meters
Casting Beds : Total 10 As Natural curing time is more hence No of beds are more and average beds for production per day comes to 3.33. (1st day 4 , 2nd Day 3 & 3rd Day 3 so average 3.33)
4 Total Area for extrusion + batching plant + other + storage of casted slab. 6 Acres
as storage of slab is done outside the extrusion beds area with special cranes
3.5 Acres
as storage of slab is done adjunct to extrusion beds with special extended crane arms
5 Investment to Set-up Plant For Residential : Approx. 16.50 Cr
For Commercial : Additional 3 Cr
For Residential : Approx. 3.30 Cr
For Commercial : Additional 50 Lakhs
6 Labour Cost Cost of Labor per Sq. Mtr – Rs. 90/- Total 23 Nos. Need Highly skilled labor for Hi-tech M/c. so the cost is high. Cost of Labor per Sq. Mtr – Rs. 48/- Total 23 Nos. average skilled labor can do this job
7 Cost of Cutting Blade Cost for Cutting blade with European cutter : Rs. 26/- Cost for Cutting blade. (we have assumed 2 Nos. of Chinese cutter = 1 no of European cutter) : Rs. 18/-
8 Approx. Yearly Production 1,60,000 Sq. Meters 1,33,000 Sq. Meters
9 Approx. Production Cost per Sq. Meter For Residential : Per Year Cost : Rs. 26.50 Cr (Rs. 1985 / Sq. Meter) For Commercial : Per Year Cost : Rs. 34.75 Cr (Rs. 2609 / Sq. Meter) For Residential : Per Year Cost : Rs. 20.83 Cr (Rs. 1563 / Sq. Meter) For Commercial : Per Year Cost : Rs. 28.75 Cr (Rs. 2157 / Sq. Meter) Savings – 5.67 Cr
10 Return on Investment (ROI) in Months For Residential : 36 Months
For Commercial : 44 Months
For Residential : 5 Months
For Commercial : 6 Months
11 Curing of Concrete slab by Heating system Steam Curing provided Underneath above steel beds. (Steam generated by Boilers) Natural curing. Taking advantage of our Hot & Humid Climate & also being open to sky.
12 Type of Extrusion Machine Modular construction. One size One Machine.
13 Design of Extrusion Machine Highly Automated, Computerized with Sensors. Design to counter their climate & offset the cost of their costly manpower. Simple Design. Start & Stop Functionality. Needs basic Technical Manpower to operate & maintain which is very economical.
14 Capacity & Height of Hopper of Extrusion M/c. Capacity of Hopper 1.5 cubic meter & Height of Hopper is Very high. Capacity of Hopper 1 cubic meter & is more horizontal plane & very Low in Height.
15 Concrete Mix Delivered to Extrusion M/c by… Shuttle system + Overhead cranes or with Overhead Crane & Skip Bucket. Mini Dumpers are used which Runs on Diesel. + Can be used for other work in the plant like Pulling the steel strand from one end to other & additional construction activity can be done.
16 Concrete Mix Delivery Time & Cost With above system Very High & Very Costly to operate & Maintain + high power consumption. With above system Very Fast, Cheap & Easy to Operate & Maintain
17 Concrete mixer & Batching plant for zero slump concrete. European & our plant material like Cement, Aggregate & Sand used are same. One can compare Results of Hollow core slabs & Test blocks produce from their respective Batching plants and know the differences Very costly & Hi-fi system & Installed at the height of more than 30 feet. Simple & Specific to Use & Requirement. Installed at about max. 8 feet height
18 Power Consumption & Requirement Installed capacity about 350KW. Consumption is Very high as there are lot of high rated capacity machines + more No. of Cranes + Boiler + Covered plant need more illumination Installed capacity about 175 KW. Consumption of power is Low as less No. of Cranes + Natural curing , No Boiler + open to sky hence does not need illumination in day.
19 Import duty on M/c & spares Very High. High priced M/c & High price spares hence more costly Very Low. Low price m/c & Low price spares hence Less import duty.
20 Time for Plant Installation etc. Approx. 9 months as industrial shed and huge overhead cranes are installed. Within 3 to 4 months
21 Flexibility of shifting plant Very difficult in case of Labor Unrest Very simple & Easy.
22 Shipping of slabs to site. Need to pay additional Taxes, Govt. duties as manufactured outside the Project site. No need to pay additional Taxes, Govt. duties, as slabs can be manufactured at the Project site.